Non-Compliance detail


  
Summary
 
Licence number: 4197
Annual Return Start: 01 Apr 2016
Annual Return End: 31 Mar 2017
Date Received: 30 May 2017
 
Licence Condition numberType of non-complianceEPA actionsNo. of times occurred
L3.1 Concentration limits for TSS & BOD exceeded on occasion. Facility at capacity with no in-built flexibility to improve treatment performance to include new monitoring point. Construction works to upgrade facility scheduled for 2019. EPA has written to licensee regarding non-compliance and relevant action 3
O6.3 Wet weather event caused tree roots to be caught in wet well, inducing airlocks in the pumps, restricting pump flows, leading to overflow from the valve pit. Blockage removed from the pumps and the airlocks rectified which ceased the overflow EPA to monitor future compliance with this condition 1